On this page

Two conditions change the selection immediately:

  • Reactive or motor-driven loads (compressors, pumps, power tools, induction motors): Power factor below 1.0 makes apparent power (VA) higher than real power (W), and locked-rotor startup draws 3x to 7x running current for 0.5 to 3 seconds. Size to the inverter's VA and surge-duration limits, not just continuous W.
  • Sustained high-draw operation (>= 3 hours) and low battery voltage: Worst-case DC input current occurs at the inverter's low-voltage cutoff (V_min) under cable and battery sag, not at nominal battery voltage. Continuous loads lasting 3 hours or more require a 1.25x multiplier on DC conductor ampacity and overcurrent sizing.

This guide is part of the Inverter Systems hub and covers output rating, concurrent load math, surge verification, and worst-case DC input current for 12V, 24V, and 48V nominal systems (<= 60V DC bus).


Baseline Specifications and System Boundaries

Parameter 12V Nominal 24V Nominal 48V Nominal Engineering Rule / Check
LiFePO4 Nominal / Absorb 12.8V / 14.2–14.6V 25.6V / 28.4–29.2V 51.2V / 56.8–58.4V Usable DoD 80–90% (default 85%)
AGM / Lead-Acid Nominal 12.0V / 14.2–14.8V 24.0V / 28.4–29.6V 48.0V / 56.8–59.2V Usable DoD 50%; keep bus <= 60V DC
Illustrative V_min at Terminals 10.5–11.0V 21.0–22.0V 42.0–44.0V Check inverter manual for exact low-voltage cutoff
Minimum Fuse Voltage Rating >= 32V DC >= 32V DC >= 60V DC Must be >= max actual charging voltage (58.4V exceeds 58V-rated terminal fuses)
AC Output Baseline 120V / 60Hz (NA) 120V / 60Hz (NA) 120V / 60Hz (NA) UK/AU regional systems: 230V / 50Hz

Note: All battery and DC bus voltages remain strictly <= 60V DC. Check the inverter, battery BMS, and charger nameplates for exact cutoff and maximum charge voltages before finalizing fuse and cable selections.


Core Sizing Formulas (Plain Text)

  1. Concurrent Continuous AC Demand (W and VA):

    P_ac_total (W)  = sum of concurrent continuous load watts
    S_ac_total (VA) = sum of (load W / load Power Factor)
    

    Select an inverter whose continuous W rating >= P_ac_total and continuous VA rating >= S_ac_total.

  2. AC Output Current (for AC breaker and branch check):

    I_ac (North America 120V/60Hz) = S_ac_total / 120V
    I_ac (UK/AU 230V/50Hz)         = S_ac_total / 230V
    
  3. Worst-Case Continuous DC Input Current:

    I_dc_max = P_ac_total / (V_min_terminal * inverter_efficiency)
    

    Use the inverter's actual low-voltage cutoff at the DC terminals (V_min_terminal) and its full-load efficiency from the datasheet (typically 0.85 to 0.92, or 0.85 as a conservative baseline).

  4. Continuous-Duty Multiplier (>= 3 Hours):

    I_dc_design = I_dc_max * 1.25
    

    Apply 1.25x whenever the continuous load runs for 3 hours or longer.

  5. Worst-Case Surge DC Current:

    I_dc_surge = P_ac_surge / (V_sag_terminal * surge_efficiency)
    

    Check I_dc_surge and its duration (in seconds) against:

    • Inverter surge rating and maximum surge time (e.g., 2x continuous for 2–5 seconds).
    • Battery BMS peak discharge current and peak time window.
    • Candidate DC fuse time-current curve (the fuse must stay below its minimum melting curve for the full surge duration).

Illustrative DC Current and Surge Comparison (2,000 W Continuous / 4,000 W Surge)

Illustrative assumptions: 2,000 W continuous AC load (PF = 1.0), 4,000 W startup surge for 2 seconds, 85% continuous efficiency (0.85), 82% surge efficiency (0.82), and LiFePO4 terminal V_min of 11.0V (12V), 22.0V (24V), and 44.0V (48V). Verify actual efficiency and cutoff voltages on your inverter nameplate.

System Voltage V_min (Terminal) Continuous DC Current (I_dc_max) >= 3h Design Current (1.25x) 4,000 W Surge DC Current (I_dc_surge) Recommended Bus Suitability
12.8V LiFePO4 11.0V 213.9 A 267.4 A 443.5 A (2s) High cable mass; tight BMS/fuse margin above 2,000 W
25.6V LiFePO4 22.0V 107.0 A 133.7 A 221.7 A (2s) Balanced for 2,000–3,500 W mobile/marine systems
51.2V LiFePO4 44.0V 53.5 A 66.8 A 110.9 A (2s) Preferred for >= 3,000 W continuous or heavy motor starts

AC output equivalent at 2,000 W (PF = 1.0): 16.7 A at 120V/60Hz (North America) or 8.7 A at 230V/50Hz (UK/AU). At PF = 0.8, apparent power rises to 2,500 VA (20.8 A at 120V; 10.9 A at 230V).


Step-by-Step Sizing and Verification Procedure

  1. Inventory Concurrent Loads (Do Not Sum Non-Concurrent Peak Nameplates):

    • List every AC device that can run simultaneously. Record running W, power factor (PF), and startup surge W (or locked-rotor amps LRA * V_ac).
    • Separate resistive loads (heaters, kettles, PF = 1.0, 1x surge) from inductive/capacitive loads (compressors, pumps, microwaves, PF = 0.6–0.85, 3x–7x surge).
    • Compute P_ac_total (W) and S_ac_total (VA). Add the single largest motor/compressor startup surge on top of the other running continuous loads to establish P_ac_surge.
  2. Select Inverter Rating and Check Regional AC Spec:

    • Choose a continuous W and VA rating >= P_ac_total and S_ac_total.
    • Confirm output voltage and frequency match the target market (120V/60Hz for North America; 230V/50Hz for UK/AU).
    • Confirm the inverter's surge W/VA and surge duration (in milliseconds or seconds) exceed P_ac_surge for the motor's actual start time.
  3. Calculate Worst-Case DC Input Current:

    • Read V_min (low-voltage cutoff) and full-load efficiency from the inverter datasheet.
    • Calculate I_dc_max = P_ac_total / (V_min * efficiency).
    • If the load runs >= 3 hours continuously, multiply by 1.25 to get I_dc_design.
  4. Verify Battery BMS and DC Fuse Coordination:

    • BMS continuous & peak: Confirm the battery bank's combined BMS continuous discharge rating >= I_dc_max and BMS peak current/duration >= I_dc_surge for the full startup time.
    • Fuse voltage rating: Confirm fuse max voltage >= max actual charging voltage (for 48V LiFePO4 charging to 58.4V, use >= 60V DC-rated fuses such as Class T; do not use 58V-rated terminal fuses).
    • Fuse AIC (Interrupt Rating): Confirm prospective fault current of the battery bank <= fuse AIC at operating voltage (LiFePO4 banks have very low internal resistance and require high-AIC fuses such as Class T).
    • Time-current curve: Plot I_dc_surge and its duration against the candidate fuse's time-current curve to verify it will not nuisance-blow, while keeping fuse_rating <= cable_ampacity.
  5. Size DC Feed Cables by Both Voltage Drop and Ampacity:

    • Measure round-trip length (2 x one-way distance) in feet (and meters).
    • Calculate voltage drop using 75°C copper resistivity (0.02097 ohm·mm²/m). Keep inverter DC feed drop <= 3% at I_dc_max (non-critical loads <= 10%).
    • Select the larger conductor size between the <= 3% voltage-drop requirement and the derated ampacity requirement (>= I_dc_design).
    • Honor terminal temperature limits (typically 75°C on inverter studs and fuse holders, even when using 105°C-rated wire). Use fine-strand marine/UL-listed copper cable; avoid undersized SAE J1128 thin-wall automotive wire and Copper-Clad Aluminum (CCA) cable.

Sign-Off Criteria

Before energizing the inverter circuit, verify all six engineering checks pass:

  • Inverter continuous W >= P_ac_total AND continuous VA >= S_ac_total.
  • Inverter surge W/VA and surge time window >= worst-case concurrent startup load and motor start duration.
  • Battery BMS continuous rating >= I_dc_max and BMS peak rating/duration >= I_dc_surge for the full surge duration.
  • DC fuse rating <= derated cable ampacity (at 75°C terminal limit) AND >= I_dc_design (1.25x for >= 3h loads), with surge point safely below the fuse's minimum melting curve.
  • DC fuse voltage rating >= maximum charging voltage (e.g., >= 60V DC for 58.4V absorb) AND fuse AIC >= battery bank prospective fault current.
  • Round-trip DC cable voltage drop <= 3% at I_dc_max, using pure copper conductor (no CCA or SAE J1128 trap).

Common Failure Modes

  • Low-Voltage Cutoff (LVC) Trip During Motor Start: The battery has sufficient state of charge, but cable resistance or a long round-trip run causes terminal voltage to sag below V_min during the 0.5–2 second I_dc_surge, tripping the inverter LVC. Fix by shortening the DC run, upsizing AWG/mm², or moving to a higher nominal bus voltage (24V or 48V).
  • BMS Overcurrent Lockout Before the Fuse Blows: High-surge inverters on 12V LiFePO4 banks can exceed a single battery's 1C–2C BMS peak limit (e.g., > 200–300 A for > 1 second), causing the BMS FETs to open and shut down the entire DC bus. Parallel additional batteries within manufacturer limits or step up to 24V/48V.
  • Nuisance Fuse Blow or Under-Rated Fuse Voltage: A fast-acting fuse sized tightly to I_dc_max without checking the time-current curve opens during repeated compressor starts. Separately, using a 58V-rated terminal fuse on a 48V LiFePO4 bank charging at 58.4V exceeds the fuse's DC interrupt voltage rating and risks arc-flash failure during a fault.
  • VA Overload on Inductive Loads: Running a 1,200 W pump or microwave at PF = 0.7 requires 1,714 VA; a 1,500 W / 1,500 VA inverter trips on overcurrent even though real watts are below 1,500 W.
  • Terminal Overheating from 75°C Limit or CCA Cable: Sizing conductor ampacity to a 105°C jacket rating on 75°C-rated inverter lugs, or using Copper-Clad Aluminum (CCA) / thin-wall SAE J1128 wire, overheats studs, melts insulation, and increases voltage drop under sustained >= 3h loads.