For broader pass-through power sharing, charging ceilings, and battery expansion limits, see the Pass-Through and Expansion Overview.
How AC Pass-Through Switchover Works
In an offline pass-through topology, the AC output is tied to the AC input through an electromechanical or solid-state transfer relay whenever incoming power is valid:
[AC Input: 120V/60Hz or 230V/50Hz]
|
+---> [AC-DC Charger] ---> [Internal Battery (<= 60V DC)] ---> [DC Ports (0 ms)]
| |
v (Normal: Relay Closed) v (Outage / Out-of-Window: Relay Open)
[Transfer Relay] <-------------------- [DC-AC Inverter]
|
v
[AC Output Receptacles]
Two timing and electrical behaviours govern what happens at the receptacles:
- AC Output Interruption (
t_transfer): When AC input fails, the controller must detect the fault (t_detect), open the input relay (t_relay), and ramp the DC-AC inverter to rated voltage (t_inv_start). The total dead time is:t_transfer = t_detect + t_relay + t_inv_startAt North America's 120V / 60 Hz baseline, one full AC cycle lasts1 / 60 Hz = 16.67 ms(half-cycle =8.33 ms). In UK/AU 230V / 50 Hz regions, one full cycle lasts1 / 50 Hz = 20.0 ms(half-cycle =10.0 ms). A 10 ms transfer window drops roughly half a cycle; a 30 ms window drops nearly two full cycles. - DC Output Continuity (0 ms): USB-C, 12V/24V regulated DC ports, and DC barrel outputs draw directly from the internal battery and DC-DC converters, not from the AC transfer relay. They experience 0 ms interruption when AC input drops.
EPS vs. UPS Claims and Load Behaviour
Manufacturers label pass-through switchover as UPS (Uninterruptible Power Supply) or EPS (Emergency Power Supply) based on the transfer duration. Neither is a true online double-conversion UPS (0 ms, where the inverter runs 100% of the time).
| Classification / Load Type | Typical Transfer Time (t_transfer) |
AC Cycles Lost (60 Hz / 50 Hz) | Ride-Through Mechanism & Governing Threshold | Expected Behaviour on Switchover |
|---|---|---|---|---|
| Online Double-Conversion UPS (Reference baseline, rare in portable stations) | 0 ms |
0 / 0 |
Continuous DC-to-AC inversion; input only charges battery | Zero interruption; immune to input frequency/phase steps |
| Station "UPS" Mode | <= 10 ms to 15 ms (check nameplate/spec) |
0.6–0.9 / 0.5–0.75 |
Relies on load PSU bulk capacitor holdup time (t_holdup) |
Keeps most desktop PCs, routers, and monitors running if t_holdup > t_transfer |
| Station "EPS" Mode | 20 ms to 30+ ms (check nameplate/spec) |
1.2–1.8+ / 1.0–1.5+ |
Exceeds bulk capacitor holdup on heavily loaded electronics | Sensitive electronics commonly reboot; lighting, heaters, and fridges ride through |
| Sensitive Switch-Mode Electronics (PCs, NAS, network gear, CPAP AC bricks) | Governed by PSU t_holdup (typically 10–16 ms at full load) |
Must stay below t_holdup |
Bulk DC bus capacitors discharge during t_transfer |
Clean ride-through if t_transfer < t_holdup; hard reboot or brownout fault if t_transfer >= t_holdup |
| Inductive / Motor Loads (120V/230V compressors, fans, pumps) | Tolerates 20–30 ms gap, sensitive to phase step |
1–2 cycles |
Rotor inertia carries shaft; inrush occurs if inverter restarts out of phase | Usually rides through short transfers; out-of-phase reconnection can trip inverter surge limits |
| Resistive Loads (Heaters, kettles, incandescent lamps) | Tolerates 30+ ms |
2+ cycles |
Thermal inertia; no internal logic or capacitors | Brief flicker or minor heat dip; resumes immediately without fault |
Note on illustrative values: Transfer times (10–30 ms) and PSU holdup times (10–16 ms) vary by hardware design and load percentage. Always verify the exact t_transfer specification on the portable station datasheet and the holdup rating on the connected power supply.
Verification and Sizing Steps
- Check Nameplate AC Ratings (120V/60Hz or 230V/50Hz): Record the station's maximum pass-through current/wattage and its inverter-only continuous and surge wattage. In many stations, pass-through allows higher current (e.g., 15 A / 1,800 W at 120V AC, or 10 A / 2,300 W at 230V AC) than the internal inverter can sustain once grid power fails.
- Verify Transfer Time and Trip Windows: Check the datasheet for the published
t_transfer(ms) and the AC input voltage/frequency trip thresholds (undervoltage, overvoltage, and frequency tolerance in Hz). - Match Load Holdup Time (
t_holdup) tot_transfer: Confirmt_holdup > t_transferfor critical AC electronics. Where a critical load (such as a router or CPAP) accepts DC input, bypass the AC transfer relay entirely by powering it from the station's DC output ports (0 msswitchover) and verify the DC port's continuous current/wattage limit rather than assuming a universal 120 W car-socket ceiling. - Verify Battery Reserve and Inverter Load Capacity: Size usable battery capacity (
Wh_usable) for the expected outage duration after accounting for inverter conversion efficiency and idle tare draw:Runtime (h) = (Nominal_Wh * Usable_DoD * Inverter_Eff) / (Load_W + Inverter_Idle_W)(Illustrative example: a 1,024 Wh LiFePO4 station at 85% default usable DoD, 88% inverter efficiency, and 20 W idle draw supporting a 150 W load yields(1024 * 0.85 * 0.88) / (150 + 20) = 4.5 hours.) - Check Cold-Charging Constraints for Standby Use: If the station is staged in an unheated cabin, vehicle, or boat below
+5 °C (41 °F), verify the BMS minimum charge temperature on the datasheet. Below0 °C (32 °F), charging is hard-blocked unless the battery is self-heated—meaning AC pass-through can feed the load, but the internal battery will not recharge while cold.
Sign-Off Criteria
- Transfer Margin: Published
t_transferis strictly less than the connected critical load's ratedt_holdup(or the critical load is moved to a0 msDC port). - Inverter-Only Continuity: Total connected AC watts (continuous and motor starting surge) do not exceed the station's inverter-only continuous and surge ratings—not just its pass-through wall rating.
- Regional Input Match: AC input voltage and frequency match the local supply (
120V / 60Hzin North America;230V / 50Hzin UK/AU) within the station's published trip window. - Thermal Readiness: Ambient storage/operating temperature is above the BMS charge cutoff (
> 0 °C / 32 °F, and verified above+5 °C / 41 °Fif applicable) whenever the station relies on pass-through to maintain battery state of charge.
Failure Modes
- Relay Chattering on Unstable Generators or Shore Power: If an AC generator or long shore-power cord sags in voltage or drifts in frequency near the station's trip threshold, the transfer relay rapidly cycles between pass-through and inverter mode, causing repeated
t_transferdropouts and thermal stress on the relay contacts. - Pass-Through Overload on Outage: Connected loads sized up to the wall pass-through limit (for example, 1,800 W at 120V AC) exceed a smaller internal inverter (for example, 1,200 W continuous). The system runs normally while grid power is present, then trips the inverter on overload the instant grid power fails.
- Holdup Underrun Under High PSU Load: A computer or server power supply that rides through a
15 msswitchover at 30% load drops out at 80% load because bulk capacitor holdup time shrinks as output current rises. - Phase-Step Surge on Inductive Loads: Because offline transfer relays do not always phase-lock the inverter to the dying AC waveform before closing, a sudden phase jump across a running compressor or transformer core can trigger an instantaneous overcurrent trip on the inverter.
- Silent Battery Depletion in Freezing Standby: A station left in pass-through mode below
0 °C (32 °F)continues passing grid power to the output while the BMS blocks charging; when an outage finally occurs, the battery is at a lower state of charge than expected.